IT/LAN Upgrade

Upgrade IT/LAN at (6) Historic Buildings at Park Headquarters

Project: IT/LAN Upgrade

Title:

Description:

IT/LAN Upgrade

Upgrade IT/LAN at (6) Historic Buildings at Park Headquarters

Tribal is contracted by the National Park Service to replace and expand all the IT and LAN cabling and networking in five headquarters buildings at Crater Lake National Park (1 building was removed since the project was named).
The project schedule is to complete 120 days from NTP.
The project includes:
  • Fiber optic cabling, splicing and testing to extend and repair building data service and interconnection
  • Install approximately 13 miles of Cat 6 cabling in new conduit to provide 630 new voice and data ports within 5 buildings
  • Conduit is installed in existing crawl spaces, attics, walls and surface mounted
  • Extending fiber optic cabling to establish one new Main Distribution Frame (MDF) and eight new Intermediate Distribution Frames (IDFs)
  • Maintaining the historic integrity of each building’s finishes during the installation
  • Demolition and finish repairs as needed for wall, ceiling and floor data conduit access
  • Maintain fire ratings at rated wall and floor penetration
  • Install ventilation in new IT rooms